MARKHAM
← EngagementsCase file — Logistics · 2023–2024MKM-E-2023-071 · Client-approved · Anonymised

Rescuing a stalled network consolidation

ClientLogistics operator
Duration12 months (rescue)
CapabilitiesImplementation oversight
Systems deliveryHolisticAutomation
84%Of the original value case recovered, verified at month 26
14 → 4Workstreams after re-sequencing to one drawn phase
6 wksFrom arrival to an honest baseline the board accepted
12 moRescue duration, arrival to verified delivery

Recovered value verified against the original month-0 case under the Markham Verification Standard at month 26.

01

The situation

A logistics operator was fourteen months into a network consolidation that reported green and shipped nothing. Fourteen workstreams, three steering committees, a programme office of twenty — and a depot network that still ran exactly as it had on day one. The integrator’s dashboard showed 71% complete. The operation showed no change a customer or a cost line could detect.

The board did not ask Markham to run the programme. It asked for the truth about it, and then for a way to keep whatever value was still alive.

02

What the diagnostic found

Six weeks of forensic baseline work established what 71% complete meant: 71% of activities started, 9% of outcomes delivered. The original value case had never been baselined — benefits were claimed against a forecast that moved quarterly. Of the fourteen workstreams, four carried 90% of the recoverable value; the other ten existed because stopping them had no owner.

The recoverable case was re-priced honestly at 84% of the original — less than the promise, more than the board feared, and for the first time a number with evidence under it.

03

How Markham helped

The rescue was a re-sequencing, not a restart. Ten workstreams stopped in one board decision; the four that mattered were re-drawn as a single phase with frozen baselines, named owners and a weekly outcome cadence. HolisticAutomation took over the systems integration under a re-cut contract with outcome milestones; Markham held oversight, contracted to the board.

Delivery ran twelve months from arrival. Verification at month 26 — against the original case, not the re-forecast — confirmed 84% recovered. The remaining 16% was written off in public, in the board minutes, which is where write-offs belong.

04

Impact in detail

MeasureMonth 0Month 26Change
Original value case recovered9% delivered84%Verified
Active workstreams144−10
Depots consolidated0 of 99 of 9Complete
Programme run-rate cost$1.1M/mo$0.4M/mo−64%

All readings verified against the original month-0 case under MKM-F-003 — not against any re-forecast.

05

What we took from it

a

Activity percentages are not progress. The gap between 71% of tasks and 9% of outcomes is where stalled programmes hide.

b

An honest baseline was the rescue. Once the board had a true number, every subsequent decision took days instead of months.

c

Writing off the unrecoverable 16% openly bought the credibility that delivered the 84%. Rescues fail when they keep promising the original number.

Discuss a similar situationThe operating model used